First let me say that a person closer to the support for the TEPCO than I am confirms the suspicion that the Japanese regulatory system never accepted the beyond design basis safety initiatives used in the U. S.. So the damaged reactors had no instructions for what to do when they got hit with a beyond design basis earthquake and Tsunami. That resulted in the total loss of electrical power. The resulting damage would have been much less severe, however, if the TEPCO operators had kept the water level up in the spent fuel pit (something their diesel fire pumps could do well) and if they had started seawater cooling of the cores of Units 1-3 earlier. These are the kind of instructions that would exist in the U. S. and did not in Japan.
I bring this up to say that I don't think advanced reactors are necessary to avoid the damage we are witnessing in Japan.
But I got usefull clarification of the advanced cooling system of the AP1000, the only truly advanced nuclear reactor available at the moment in my opinion, that I want to pass along. The basic design principle of the AP1000 is to have an inner steel containment vessel inside a shaped concrete outer containment. Current nuclear plants have the steel liner in contact with the contrete and the steel inner is not sufficient to contain the pressure without the concrete, the AP1000 steel inner is much thicker. Air flow between the steel inner and concrete outer is what cools the plant if offsite power is lost. This is aided by a large tank of water that coats the outer surface of the steel inner containment with water (for evaporative cooling) for 3 days. This allows the core to cool a lot, the decay fissions would be nearly totally gone so there would be a fraction of a percent of the normal power to be removed. After that point, you have 5 to 35 days to put more water in the tank (using a fire hose or whatever you have) or the pressure in containment would begin to rise. It is 5 days at minus 40 F and 35 days at 115 F (the cooling is apparently better at higher temperatures (not intuitively obvious why)). The inner containment would never be breached if water was not put back in the tank but the core might be damaged. In other words, the public would not be at risk because the radioactivity would be contained but the utilities economic interest in the plant is at considerable risk if the water is not put back in the plant within a week to a month after power is lost.
I am not trying to imply that AP1000s are perfect, only that they do not have the same reliance on power that was an issue on the Japanese plants. If you are interested, this link should get you to a lot more informaiton on AP1000s:
http://www.ap1000.westinghousenuclear.com/
The only new plants that have "moved dirt" in the U. S. are AP1000s. TVA is planning to finish Belefonte but it is very old technology that started construction in the 70s and is planning to resume (why would be a good question). TVA will start up Watts Bar 2 late this year or early next. It is also old technology (but better than Belefonte IMHO). No new BWRs are currently planned in the U. S. (not that they are unsafe or inferior, that is just the status).
Jim
I bring this up to say that I don't think advanced reactors are necessary to avoid the damage we are witnessing in Japan.
But I got usefull clarification of the advanced cooling system of the AP1000, the only truly advanced nuclear reactor available at the moment in my opinion, that I want to pass along. The basic design principle of the AP1000 is to have an inner steel containment vessel inside a shaped concrete outer containment. Current nuclear plants have the steel liner in contact with the contrete and the steel inner is not sufficient to contain the pressure without the concrete, the AP1000 steel inner is much thicker. Air flow between the steel inner and concrete outer is what cools the plant if offsite power is lost. This is aided by a large tank of water that coats the outer surface of the steel inner containment with water (for evaporative cooling) for 3 days. This allows the core to cool a lot, the decay fissions would be nearly totally gone so there would be a fraction of a percent of the normal power to be removed. After that point, you have 5 to 35 days to put more water in the tank (using a fire hose or whatever you have) or the pressure in containment would begin to rise. It is 5 days at minus 40 F and 35 days at 115 F (the cooling is apparently better at higher temperatures (not intuitively obvious why)). The inner containment would never be breached if water was not put back in the tank but the core might be damaged. In other words, the public would not be at risk because the radioactivity would be contained but the utilities economic interest in the plant is at considerable risk if the water is not put back in the plant within a week to a month after power is lost.
I am not trying to imply that AP1000s are perfect, only that they do not have the same reliance on power that was an issue on the Japanese plants. If you are interested, this link should get you to a lot more informaiton on AP1000s:
http://www.ap1000.westinghousenuclear.com/
The only new plants that have "moved dirt" in the U. S. are AP1000s. TVA is planning to finish Belefonte but it is very old technology that started construction in the 70s and is planning to resume (why would be a good question). TVA will start up Watts Bar 2 late this year or early next. It is also old technology (but better than Belefonte IMHO). No new BWRs are currently planned in the U. S. (not that they are unsafe or inferior, that is just the status).
Jim

LCHIEN
Loring in Katy, TX USA

Comment