To make a long story short, we did an addition and a lot of things are left unfinished (insulation in floor above full basement, final grading of soil around foundation, exterior paint, door knobs for new doors, screens on windows, etc.). The builder expects to do final grading, install a gutter that is in the contract, and he wants full final payment.
I want it all done, or I don't want him back. He says the contract doesn't list those things, but my take is that is part of the finished job just like the contract doesn't need to spell out to use construction adhesive between joists and sub-floor.
He has threatened to place a lien against our home, but I'm not afraid to fight it and counter-sue. Though a friend of mine suggested I offer him arbitration. I may have an ace up my sleeve in that we've actually already paid him more than the amount in the contract, so should it boil down to just items explicitly listed, then the extra payment for additional excavation, sill replacement, etc. were never in the contract...
What would you advise? Surely there are some of you here that have been on both sides of this kind of dispute. I called two friends of mine that are contractors and they said I'm being perfectly reasonable to expect all those things included because they are either required by code (insulation) or are considered part of the finished product.
Regards,
~ Fred
I want it all done, or I don't want him back. He says the contract doesn't list those things, but my take is that is part of the finished job just like the contract doesn't need to spell out to use construction adhesive between joists and sub-floor.
He has threatened to place a lien against our home, but I'm not afraid to fight it and counter-sue. Though a friend of mine suggested I offer him arbitration. I may have an ace up my sleeve in that we've actually already paid him more than the amount in the contract, so should it boil down to just items explicitly listed, then the extra payment for additional excavation, sill replacement, etc. were never in the contract...
What would you advise? Surely there are some of you here that have been on both sides of this kind of dispute. I called two friends of mine that are contractors and they said I'm being perfectly reasonable to expect all those things included because they are either required by code (insulation) or are considered part of the finished product.
Regards,
~ Fred



Comment